Progress invoices on a building job: invoicing as the work progresses, calculation and mandatory details

On a worksite lasting several weeks, waiting until the end to invoice puts pressure on cash flow. A progress invoice lets you invoice as the work advances. How to calculate it, what it must include, and how to finish with the final invoice.

These pages describe French rules. The translations do not constitute an adaptation to the law of another country.

4 Oct 2026 · 7 min read

In short: a progress invoice, also called a stage invoice, is used to invoice a job as the work is carried out, for example every month, instead of waiting until the end. It is an invoice in its own right: same mandatory details, a number in your continuous sequence, and it can no longer be changed once issued. The amount is the difference between the cumulative work done and the total already invoiced. The final invoice closes the contract.

A bathroom renovation is often invoiced in two stages: a deposit on signing and the final balance on completion. But on a worksite lasting several weeks or months, waiting until the end to be paid puts a heavy strain on cash flow. Progress invoices address this: you bill as work is actually completed, for example at the end of each month.

A progress invoice is a full invoice in its own right. It carries all the mandatory mentions of an invoice (see impots.gouv.fr), it receives a number in the same continuous sequence as your other invoices, and once issued it can no longer be changed: it is corrected by a credit note or by a corrective invoice that refers to it.

The calculation always follows the same logic. Start with the contract amount: the signed quote and signed amendments. Multiply it by the progress achieved at the date of the progress invoice, line by line or overall: this is the cumulative value of work completed. Subtract the cumulative amount already billed in previous progress invoices to obtain the current progress invoice amount. Then deduct the allocated share of the deposit and any retention specified in the contract. The remainder is the net amount payable.

Example: a €20,000 contract excluding VAT, a 30% deposit already invoiced, and 40% progress at the first progress invoice. Cumulative progress amounts to €8,000 excluding VAT. Nothing has yet been invoiced through progress invoices, so the progress invoice covers €8,000 excluding VAT. If the deposit is applied in proportion to progress, 40% of the deposit is deducted, or €2,400 excluding VAT, with the corresponding VAT. The customer pays the difference.

Two rules prevent errors. Compare cumulative amounts, rather than just the amount of each progress invoice: a new progress invoice can be for less than the previous one if the additional progress is smaller. If an issued progress invoice overstates the cumulative value of work completed, correct it with a credit note or corrective invoice referencing it; do not offset the error by simply invoicing less on the next one. The cumulative amount invoiced must not exceed the contract amount: for additional work, have an amendment signed first.

For VAT, each line retains the rate from the quote or amendment, and the deposit deduction is broken down into the amount excluding VAT and the VAT amount, rate by rate, because the deposit has already been subject to VAT. For these services, VAT generally becomes due on receipt of deposits or payment of the price, or on debits if you have exercised that option. Even with this option, a deposit received before the debit makes VAT due as soon as it is received.

In addition to the usual information, a progress invoice benefits from clearly stating: the quote and amendment references, its sequence number (“Progress invoice No. 3”) and the period covered, the contract amount, progress, the cumulative value of work completed, the cumulative value of previous progress invoices with their numbers, deposits deducted, the retention amount, then the net amount payable and its due date.

At the end of the work, the final invoice sets out the final account: 100% of the contract, less all progress invoices and deposits that have not yet been applied. Any retention remains withheld until its release.

In Okivo, you create a progress invoice from the signed quote, with progress entered by line or overall and the period covered. Okivo calculates cumulative progress, subtracts what has already been invoiced, deducts the remaining deposit and the retention specified in the contract, and prints the references of previous progress invoices and deposits. It rejects progress that goes backwards and a cumulative amount exceeding the contract. The progress invoice receives its number in your invoice sequence, and the final invoice closes the contract.

Frequently asked questions. Is a progress invoice a real invoice? Yes: it carries all the mandatory details of an invoice and gets a number in the same sequence as your other invoices.

Can a progress invoice be changed once issued? No: you correct it with a credit note or a corrective invoice that refers to it.

How is the amount of a progress invoice calculated? You start from the contract amount, multiply it by the progress achieved (the cumulative work done), then subtract the total already invoiced in previous progress invoices. You then deduct the share of the deposit applied and, if the contract provides for one, the retention.

What if the job changes? The total invoiced must not exceed the contract amount: for additional work, have a change order signed first.