Progress invoices on a building job: invoicing as the work progresses, calculation and mandatory details
4 Oct 2026 · 7 min read
Language
Payment
Can the customer retain 5% of the price until one year after acceptance of the works? Only if the contract provides for it, and never without safeguards. The rules of the 1971 law, the surety that replaces retention, and how to recover the amount.
These pages describe French rules. The translations do not constitute an adaptation to the law of another country.
In short: a retention is at most 5% of the value of the work, and it only applies if the contract provides for it. The customer cannot decide on it alone during the job. It guarantees that the defects noted at acceptance of the works are put right; in principle, it is released one year after that acceptance, unless the customer lodges a reasoned objection under the legal conditions. The details, point by point, below.
On a worksite billed through progress invoices, retention can hold back part of the payments if the contract provides for it. It guarantees that defects noted at acceptance are remedied. It is generally released one year after that acceptance, unless a reasoned objection is made under the statutory conditions; it does not extend until the end of the two-year or ten-year guarantees. For the tradesperson, it is money earned but temporarily retained: knowing the rules helps you keep track of it.
The framework is set by Law No. 71-584 of 16 July 1971, which is mandatory for private works contracts, including those with private individuals (off-plan home sales and individual house construction contracts have their own rules). The retention is no more than 5% of the value of the works. It is deducted from deposits and progress payments, and serves to secure the rectification of defects noted at acceptance of the works.
First rule: retention only exists if the contract provides for it. It must appear in the signed quote or contract, with its rate. A customer cannot unilaterally decide, during the work, to retain 5% of an invoice.
Second rule: retention is never without a corresponding safeguard. Either you provide a personal and joint-and-several guarantee from a financial institution for the same amount: no retention is then applied, and the customer cannot refuse the guarantee. Or the customer deposits the retained sum with a stakeholder accepted by both parties or, failing agreement, appointed by the president of the French tribunal judiciaire or tribunal de commerce. The law requires a customer applying retention to deposit the money (Article 1): without a guarantee or a deposit, retention is not justified in principle, and you can demand payment.
Everything starts with acceptance of the works, preferably recorded in a dated acceptance report, with or without reservations (Article 1792-6 of the French Civil Code). This also starts the tradesperson’s guarantee periods: one year for perfect completion and, depending on the work, two years for proper functioning and ten years for ten-year liability. Record this date: without it, you cannot calculate when retention is due for release.
One year after acceptance of the works, with or without defects noted, the surety is released or the deposited funds are paid to you. The only exception is where the customer has objected, giving reasons based on your failure to fulfil your obligations, and notified the surety provider or deposit holder by registered letter. Do not wait for the money to come back on its own: when it is due, send a release request to the customer and, where applicable, the deposit holder.
For VAT purposes, the released amount is not a new invoice: it has already been invoiced in your progress invoices. Receiving payment makes the VAT due, as with all your works, unless you have opted for the French debit-based VAT payment system, in which case it was already due when invoiced.
In Okivo, retention is set on the quote at a rate capped at 5 %; it is never suggested by default. You enter the security, either a surety (institution and guaranteed amount) or deposited funds, followed by the acceptance date and any reservations. Each progress invoice and the final invoice show the retained amount and cumulative retention. Okivo warns you if retention is applied without security, reminds you thirty days before the deadline and prepares the release request, ready to send.
Frequently asked questions. Is a retention compulsory? No: it only applies if the signed quote or contract provides for it, with its rate.
What is the maximum rate? At most 5% of the value of the work (French Law no. 71-584 of 16 July 1971).
Can it be replaced? Yes, by a joint and several personal guarantee from a financial institution, for the same amount: no retention is then made, and the customer cannot refuse this guarantee.
When is it released? In principle one year after acceptance of the works, with or without reservations, unless the customer lodges a reasoned objection, notified by registered letter to the guarantor or the depositary.