Job profitability: working out your real margin, job by job

An invoiced worksite is not necessarily a profitable one. How to calculate your actual margin, including hours, purchases and stock, and why to do it during the work rather than afterwards.

These pages describe French rules. The translations do not constitute an adaptation to the law of another country.

25 Sept 2026 · 6 min read

In short: a job’s margin is the amount sold excluding VAT (signed quote and change orders) minus the direct costs: the hours actually spent multiplied by a loaded hourly cost, the purchases linked to the job, and what leaves your stock. Example: €12,000 excl. VAT sold and €8,150 of direct costs give €3,850 of margin, or 32% of the amount sold. Track it during the job rather than afterwards, so you can react.

Many tradespeople only find out whether a year went well when they receive their accountant's annual accounts. Too late to know which worksites made money and which cost them. Yet calculating this worksite by worksite is straightforward, provided you record the right information as you go.

The starting point is the sales amount: the signed quote excluding VAT, plus amendments. The VAT is not yours and is not included in the calculation.

The first cost, often the most underestimated, is labour. It is not the hours allowed for in the quote, but the hours actually worked, multiplied by a fully loaded hourly cost. For an employee, this cost includes gross pay, employer contributions and paid leave contributions to the construction industry's holiday fund: it is far higher than the gross hourly wage. For yourself, allow at least the remuneration you aim to earn.

Next come purchases linked to the worksite: supplies, equipment hire, subcontracting and rubble removal. Remember items taken from your stock: the pipe, fittings or adhesive taken from the workshop have been paid for, even if they appear on none of this month’s supplier invoices.

The worksite margin is the sale value minus these direct costs. For example: a bathroom sold for €12,000 excluding VAT, 90 hours at €38 including employment costs (€3,420), €4,100 in materials, €250 in hire and €380 taken from stock. Direct costs total €8,150; the margin is €3,850, or 32% of the sale value. This margin must pay your overheads: vehicle, insurance, premises, tools and time spent preparing quotes that are not signed.

Tracking this calculation during the work means you can act. If the hours already exceed the estimate halfway through, there is still time to discuss an amendment with the customer, rethink the organisation or, at the very least, correct your next quotes. Another common leak: a completed worksite that is never invoiced in full.

In Okivo, choosing “Open a worksite” from a signed quote links the quote and its invoices to the worksite: sales and invoiced amounts are tracked automatically. Your workers log their hours, you record purchases and stock withdrawals, and Okivo calculates the margin in real time. It alerts you if hours exceed the estimate, the margin becomes negative or a completed worksite has not been invoiced. Only you and your accountant can see your employees’ hourly cost.

Frequently asked questions. How do you calculate a job’s margin? The amount sold excluding VAT, minus the labour actually spent, the purchases linked to the job and the stock withdrawals. VAT is not part of the calculation.

Which hourly cost should you use? Not the gross rate: for an employee, the loaded cost includes gross salary, employer contributions and the holiday pay paid to the building-trade holiday fund. For yourself, count at least the pay you are aiming for.

What is the margin for? To pay your overheads: vehicle, insurance, premises, tools, and the time spent on quotes that don’t get signed.